Evaluation and award: what happens after you submit

How committees examine bids, how the ranking is calculated, and how to read an award result.

6 min readUpdated 2 November 2026
Mali edition: the rules shown are this country's.Change country

Once the packages are opened, your bid disappears into a committee and you often hear nothing for weeks, sometimes months. That silence is normal, but your work does not stop: the committee can write to you at any moment, and a late reply can eliminate you. Here is what happens in that time, in order, and what you have to do.

What the committee does, in order

The evaluation committee applies the grid and the criteria written in the tender file, and nothing else. The usual order is as follows.

  1. Administrative compliance

    Are the required documents there, valid and signed? Does the bid security comply? This is where expired certificates and missing forms fall. In some files the committee accepts that a non-essential document be supplied afterwards. Do not count on it.

  2. Technical review

    Does your bid answer what was asked? The committee checks the eliminatory criteria, references, staff, equipment and schedule, and gives a score if the file provides for one. Often, a bid that does not reach the technical minimum never has its price looked at.

  3. Financial review

    The committee redoes the sums, corrects errors, adjusts prices so they can be compared, applies any preferences and looks for abnormally low bids.

  4. Ranking and final check

    It ranks the bids and proposes a winner. Some files provide at this stage for a closer check of the top-ranked firm: financial capacity, references, sometimes a visit. If it fails, the committee moves to the next one.

After the committee's opinion, the award often goes through a validation: an oversight body or the funder's no-objection, depending on the contract. That is one reason the result can take time.

Lowest evaluated bid or weighted score

The file says which of these two methods applies. Works, supplies and ordinary services most often use the first, and consulting the second.

The lowest evaluated bid. Among the bids that meet the requirements, the contract goes to the one with the lowest evaluated price. The evaluated price can differ from the price read aloud: error corrections, adjustments, preferences. A high technical score earns nothing extra here. You just have to clear the bar.

The weighted score. The committee scores technical quality and price, then combines them using the weights written in the file. The best combined score wins, even without the lowest price. This is the classic consulting case, with a financial envelope opened only for those who reached the minimum technical score.

After a consulting ranking, the contract is generally negotiated with the top-ranked firm. In a classic tender, negotiating the price is usually forbidden. With private companies and some organisations, on the other hand, it can be common: see Who is buying and which rules apply.

If the committee writes to you

The committee can ask for a clarification: an unreadable document, a date to confirm, a reference to clear up. The request comes in writing and gives a time limit, often very short.

  • Reply at once, and in writing. Watch the e-mail address and phone number you gave in the bid, including when travelling. A late reply can be treated as no reply.
  • Reply only to what is asked. You are clarifying your bid, not writing a better one.
  • You cannot change your price, or anything that would change the substance of the bid. The only usual price change is the committee's correction of a calculation error.

Do not try to reach committee members privately either. Any attempt to influence them can get your bid rejected, and bring heavier sanctions.

Preferences and abnormally low bids

Some rules grant a preference, for example to national, regional or local firms, or to small businesses. It often takes the form of a margin applied only for the comparison: the foreign competitor's price is raised for the calculation, and the contract is then signed at your real price. If you qualify, attach what the file asks for to prove it, because it is not always applied automatically.

If your price seems abnormally low, the committee can ask you to justify it. Have your quotes and price breakdown ready: see Price your financial bid.

The rule in Mali

Evaluating bids

  • The contract goes to the compliant bid evaluated as lowest, whose author meets the qualification criteria, with no negotiation (art. 49, 75 and 80). Only purely arithmetical errors may be corrected, and the commission may ask for written clarifications without changing the bid (order, art. 12.5). A variant is considered only if the dossier allows it (art. 73).[6][10]
  • A bid is inadmissible if not signed by an authorised person, if prices are missing, if the required bid guarantee is absent, or if it departs from the essentials of the dossier. A document not specified as mandatory may be supplied before provisional award. Lack of initials on each page is not a non-conformity if the bid is otherwise compliant (order, art. 12.2 and 12.3).[10]
  • Abnormally low bid: the buyer computes the average of compliant bids and treats as suspect those below that average reduced by a percentage set in the dossier (20% at most). You have 2 working days to justify your price. The bid may be rejected only if its amount does not match the economic reality of the work (art. 77; order, art. 13).[6][10]
  • The commission has 10 working days after opening to choose the provisional awardee, the technical sub-commission 5 working days. Its decisions are unanimous (order, art. 3.9 and 17.1).[10]

Preferences and SMEs

  • Community preference: a margin of at most 15% of the bid amount is granted to firms whose head office is in a UEMOA member state. The percentage is set in the tender dossier (art. 76 and 2).[6]
  • Below the award thresholds, for all types of contract, a 25% preference margin is given to Malian-origin products and to Malian-law firms whose capital is majority held by nationals. Craftsmen and craft enterprises established in Mali get an extra 5%, cumulative. The dossier must state the preference and the comparison method (2018 decree, art. 11).[11]
  • Contracts of decentralised local authorities and their establishments: a margin of at most 5% is possible for a bidder planning to subcontract at least 30% of the contract value to a Malian firm or craftsman, cumulative with the community preference (2018 decree, art. 5.2).[11]
  • Craft services are reserved for national craftsmen unless impossible for justified reasons. Where micro-enterprises can meet a need, the buyer must, unless exceptionally justified, reserve those services exclusively for them. The buyer may use an imported product only if the local equivalent is unavailable or non-compliant (2018 decree, art. 12.3 to 12.5).[11]

Extending bid validity

Your bid is valid for a period set by the file. If the evaluation runs past that period, the buyer can ask you to extend it.

Take this request seriously and reply within the time given. As a general rule:

  • you can refuse, and you then leave the competition without losing your security;
  • if you accept, you keep your price unless a clause says otherwise, and you must have the bank extend your security if its date becomes too short.

Before replying, redo your sums. Do your suppliers still hold their prices? Is the contract still profitable at this amount? Never leave a request unanswered, because your bid may drop out without you having decided it.

Reading a provisional award

The provisional award, sometimes published as an award notice, is the decision of the committee or the competent authority before the contract is signed. It usually opens a period during which bidders can challenge it, before any signature.

Depending on the country, it appears in the procurement journal, on the public portal or on the buyer's website, and bidders sometimes receive a letter. Read it carefully:

  • The winner's name and the amount. Compare with what was read at opening. A difference may be explained by a correction, or give you a question to ask.
  • The lot. Check that it really is yours.
  • The time limits. Write down the publication or receipt date at once: it is often what starts the clock for an appeal. See Challenge a decision.
  • The grounds for rejection, when they are given.

A provisional award is not yet a contract. If you are selected, do not start anything or buy anything before notification and the steps that follow. They are described in Deliver the contract and get paid.

The rule in Mali
  • The commission signs on the spot a provisional award minute (selected, excluded with reasons, price, time limits, subcontracting); it is published after validation. Rejected bidders are informed in writing and may request the reasons, the contract amount, the awardee's name and a copy of the minute: the buyer answers within 5 working days of the written request (art. 78 and 79.1).[6]
  • The buyer observes a period of at least 15 days after publication before signing the contract and submitting it for approval (art. 79.2). Then the contract is signed, approved (10 working days at the approving authority), numbered by the DGMP-DSP, and notified to the contractor. It takes effect on notification, and a final award notice is published within 15 calendar days (art. 83, 84; order, art. 15).[6][10]
  • A tender is declared unsuccessful if no bid is received, none is compliant, or all compliant bids exceed the budget. The buyer launches a new tender or consults at least three contractors or suppliers, with prior DGMP-DSP authorisation (art. 74). Where prior authorisation was mandatory and not obtained, the contract is void (art. 81.2).[6]

Always ask why you were rejected

If you lose, write to the buyer to ask why. Do this even if you do not plan to challenge anything. In most public contracts and with funders, you can obtain at least the reasons your bid was rejected, and some organisations offer a debriefing. A private company often owes you nothing, but a polite request costs little.

An answer does three things. You learn whether you fell on a document, on the technical side or on price. You fix that point for the next bid. And if the reason does not match what the file says, you have something concrete, provided you act in time. A short letter is enough: the notice reference, the lot, your request and nothing else.